Termination of Contract

AuthorCarol J. Patterson - Ross J. Altman - Stephen A. Hess - Allen Overcash
Pages497-528
ChAPtEr
497
16.01 INTRODUCTION
A termination of contract occurs when the owner tells the contractor “you’re
red,” or the contractor tells the owner, “I quit.” The issues surrounding ter-
mination, however, are rarely that straightforward. Termination of contract is a
remedy available for particular causes and defaults. Those causes and defaults
may be identied in the contract itself, or may be those causes and defaults for
which termination of contract is a remedy under the common law.
Whether a party has the right to terminate a contract is not always clear.
Even when a cause or default supporting termination can be identied,
that does not end the inquiry. Construction projects are complicated, and it is
unusual for one party to be exclusively responsible for a default or other prob-
lems that may occur on a project. How the law responds to such situations
cannot often be predicted. Moreover, even when the facts support the legal
right to terminate a contract, the adverse consequences of doing so may out-
weigh the practical benet. As a result, termination is a drastic measure, and
generally undertaken only under extreme circumstances.
Termination of Contract
niChoLAs D. siEGFriED AnD John h. tArLow
16
pat54645_03_b03_497-844.indd 497 6/28/19 1:53 PM
CONSTRUCTION LAW
498
Indeed, reported case law is replete with lengthy discussion and analysis of
numerous questions arising from contract terminations, such as the following:
Did a party have the right to terminate the contract?
Did the terminating party follow the often complex termination provi-
sions of the contract?
Should the allegedly non-performing party have the right to x the
problem before termination becomes effective?
What is the difference between termination for cause and termination
for convenience?
What happens if a party wrongfully terminates a contract?
If the termination was wrongful, what damages or other remedies are
available to the party whose performance was wrongfully terminated?
As discussed in an earlier chapter, a construction project involves a net-
work of many separate contracts. Any one of those contracts might be subject
to termination, depending on the pertinent facts. For purposes of illustrating
the principal issues involved in contract termination, as well as explaining
some of the complicating factors that arise, this chapter considers termina-
tion primarily in the context of a construction contract between an owner and
prime contractor, and addresses termination by focusing on four key topics.
First, Section 16.02 reviews the basic legal concepts of termination of a
contract as established by the common law. Second, Section 16.03 explains the
manner in which modern construction contract forms, such as those created
by the American Institute of Architects, ConsensusDocs, and the Engineers
Joint Contract Documents Committee, establish rules and procedures through
which owners and contractors deal with termination. Section 16.04 discusses
issues that commonly arise in connection with the termination of construction
contracts. Finally, Section 16.05 covers the topic of an owner’s termination for
convenience.
16.02 RIGHT TO TERMINATE UNDER THE COMMON LAW
Not all breaches of construction contracts are equal. It has been noted that
any contractually authorized breach by either party for which the contract
provides administrative redress cannot constitute a common-law breach of
contract . . . such as those addressing changes, suspension of the work, mis-
representation of site conditions, and termination for convenience. . . . [Such
contract provisions convert] what otherwise would constitute traditional
common-law breaches into a contractual right.1
1.
PhiliP l. Bruner & Patrick J. O’cOnnOr, Jr., Bruner & O’cOnnOr On cOnstructiOn law
§ 18:2
(West Group 2002) [hereinafter
Bruner & O’cOnnOr
].
pat54645_03_b03_497-844.indd 498 6/28/19 1:53 PM
Termination of Contract 499
Under the common law, a party’s right to terminate a contract for cause
is based on the concept of a “material breach” that is not excused, cured,
or waived. A breach of a contract is material only if the breach is substan-
tial enough that it “reasonably compels a clear inference of unwillingness or
inability of one party to meet substantially the contractual future performance
expectations of the other party, and of the need for the other party to mitigate
its damages.”2 Stated differently, “[a] ‘material breach’ [is] any breach that
materially impairs the interest of the non-breaching party in the future per-
formance of a contract.”3 If a party has materially breached the construction
contract, the non-breaching party may have grounds to terminate.
A party’s failure to perform may arise from a variety of circumstances.
An owner’s breach may encompass a number of failures, such as not provid-
ing the contractor with access to the site, not responding adequately to the
contractor’s requests for information, or failing to make payments in a timely
manner, to name just a few. Breach by the contractor may include, by way of
example, not completing the work in accordance with the drawings and spec-
ications, not completing the entire scope of work in accordance with time
requirements of the contract, not fullling warranty obligations, or not paying
subcontractors and suppliers timely.
While all of the events described in the preceding paragraph are examples
of breaches of contract, the difculty and the risk to each party in deciding
whether to terminate the contract on the basis of such breaches lies in part
in assessing whether the breach is material. For example, if the contractor is
one day late in completing some task on the project, is that breach signicant
enough to warrant a termination of the contract? If the contractor fails to com-
plete a portion of the work in accordance with the drawings and specications,
is the deviation so important as to constitute a material breach of contract?
Distinguishing a material breach from an immaterial breach is no easy task,
and is especially difcult in the context of a complex construction dispute:
We note parenthetically and at the outset that, except in the middle of a bat-
tleeld, nowhere must men coordinate the movement of other men and all
materials in the midst of such chaos and with such limited certainty of pres-
ent facts and future occurrences as in a huge construction project such as
the building of this 100 million dollar hospital. Even the most painstaking
planning frequently turns out to be mere conjecture and accommodation to
changes must necessarily be of the rough, quick and ad hoc sort, analogous
to ever-changing commands on the battleeld. Further, it is a difcult task
for a court to be able to examine testimony and evidence in the quiet of a
courtroom several years later concerning such confusion and then extract from
2. Id. § 18:4.
3. Id. § 18:1.
pat54645_03_b03_497-844.indd 499 6/28/19 1:53 PM

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT