Section 8.3 Dispute Resolution Procedures for Changes in the Work

LibraryConstruction Law 2016 Supp

B. (§8.3) Dispute Resolution Procedures for Changes in the Work

Article 4 of AIA Document A201-1997, General Conditions of the Contract for Construction (15th ed.), sets forth typical claim and dispute resolution procedures. In general, claims must be submitted to the architect within 21 days after occurrence of the events giving rise to the claim or within 21 days after the claimant first recognizes the conditions giving rise to the claim, whichever is later. Paragraph 4.3.2. The contractor must give...