Section 8.12 Defining Time of Performance

LibraryConstruction Law 2016 Supp

A. (§8.12) Defining Time of Performance

If no time for performance is specified, the law implies that performance will occur within a reasonable time. See ArtCraft Cabinet, Inc. v. Watajo, Inc., 540 S.W.2d 918 (Mo. App. W.D. 1976). A construction contract usually defines the time for performance. The contract may provide that the work shall be completed within a certain number of calendar days or working days from the date of commencement of the work. The contract may also provide for a specific starting...