Payment

AuthorCarol J. Patterson - Ross J. Altman - Stephen A. Hess - Allen Overcash
Pages361-392
12.01 IntroductIon
Payment and cash ow issues are often the most negotiated and litigated issues
on construction projects. Construction is all about the ow of funds from the
lender to the owner to the contractor to the subcontractors to the suppliers.
A contractor typically has to advance certain costs before receiving payment
from the owner. For example, a contractor typically will perform work for 30
days before sending its rst invoice to the owner. The owner then has 30 days
to make payment, and the owner is often entitled to withhold a portion of the
payment as retainage. As a result, a contractor may have to wait 60 days or
longer before receiving its rst payment, which may only represent 90 percent
of its billing (where the owner withholds 10 percent retainage). During that
60-day period, however, the contractor must make payment to its employees,
subcontractors, and material suppliers. Contractors and subcontractors cannot
“be expected to nance the operation to completion without receiving the stip-
ulated payments on account as the work [progresses]. . . . Advance payment is
a condition precedent to the contractor’s obligation to proceed.”1
1. Guerini Stone Co. v. P.J. Carlin Constr. Co., 248 U.S. 334, 345, 39 S. Ct. 102, 106 (1919).
12
Payment
DAVID A. SENTER
CHAPTER
361
pat54645_02_b02_283–496.indd 361 6/28/19 2:01 PM
CONSTRUCTION LAW
362
Subcontractors tend to be smaller, less well capitalized entities than gen-
eral contractors. Although not always the case, subcontractors may not be as
nancially strong as either the general contractors for whom they work or the
suppliers on whom the they rely for materials. Although subcontractors will
not receive payment from the general contractor until a specied portion of
the work is completed, subcontractors usually pay their eld personnel and
tradespeople on a weekly basis and often must pay suppliers in advance for
materials received. Placed in this nancial squeeze, subcontractors not uncom-
monly “rob Peter to pay Paul,” that is, use payments on one project to pay bills
on another.
If payment is delayed at any point in the construction chain, the contractor
or subcontractor may run out of money and/or be unable to pay its subcon-
tractors, suppliers, or tradespeople to continue working.2 The likely result is
delayed performance or nonperformance. Thus, a project’s success or failure
may depend on whether the project participants are paid promptly for their
work.
12.02 basIs For paYment
The parties’ contract should clearly describe the basis and timing for payment.
Many ways exist to structure payment in a construction contract, including
stipulated sum (lump sum or xed price), unit price, “cost plus” (cost of the
work, plus the contractor’s fee), and others.3 The traditional pricing mecha-
nism is xed price. This mechanism arises out of the Design-Bid-Build method
of project delivery. Under this method, an owner presents its plans and spec-
ications, prepared by the owner’s design professional, either to a contractor
to price, or to a group of contractors to bid. Based on those plans and speci-
cations, the owner and the contractor enter into a contract to construct the
project for a xed price, also referred to as a lump sum or stipulated sum.
A unit price contract may be used where the type of work is well dened
but the quantity is only estimated. If a contractor must bid a xed price for an
unknown quantity, its price will likely be high so as to include the quantity
risk contingency. On the other hand, with a unit-price contract, the quantity
contingency is not a signicant issue because the contractor receives a speci-
ed unit price for each of the units it installs on the project, and the contrac-
tor’s price likely will be lower.
2. Subcontractors, as a whole, le more bankruptcies than any other entity in the construc-
tion process. See Carina Y. Enhada, Cheri Turnage Gatlin & Fred D. Wilshusen, Fundamentals of
Construction Law,
aBa cOnstructiOn fOruM
2001 [hereinafter Fundamentals].
3. See id. at ch. 9 (discussing pricing mechanisms in more detail).
pat54645_02_b02_283–496.indd 362 6/28/19 2:01 PM
Payment 363
A cost-plus or cost-reimbursement contract provides that the owner will
pay or reimburse the contractor for its costs (labor, material, and equipment)
and also will pay the contractor a fee, which is usually a percentage of the
costs (e.g., cost plus 15 percent). Such contracts should contain a clear deni-
tion of “costs,” especially as the term relates to the contractor’s own person-
nel, equipment, management, and overhead. The AIA contract documents, for
example, deal with “cost” by dening the term to include labor costs; subcon-
tract costs; costs of material and equipment incorporated in the completion
of construction; costs of other materials and equipment, temporary facilities,
and related items; and miscellaneous costs.4 Obviously, such an open-ended
contract leaves the owner exposed to uncertainties and increased costs. This
exposure is often managed by using a cost-plus contract coupled with a Guar-
anteed Maximum Price, or a GMP. Such a contract involves a typical cost-plus
arrangement up to the dollar amount of the GMP. The contractor bears the risk
of any costs over the GMP, thereby reducing the owner’s risk.
Given the risks involved in cost-plus contracts, AIA Contract Document
A102–2017 provides that
The Contractor accepts the relationship of trust and condence established by
this Agreement and covenants with the Owner to cooperate with the Architect
and exercise the Contractor’s skill and judgment in furthering the interests of
the Owner; to furnish efcient business administration and supervision; to
furnish at all times an adequate supply of workers and materials; and to per-
form the Work in an expeditious and economical manner consistent with the
Owner’s interests.5
Some courts have held that such language creates a duciary relationship
between the owner and the contractor, thereby increasing the level of the con-
tractor’s duty to the owner and providing the basis for a constructive fraud
claim.6 Other courts have held that such language alone does not necessarily
create a duciary duty.7
4. AIA Contract Document A102–2017, articles 7 and 8.
5. Id. at art. 3.
6. See Jones v. J.H. Hiser Constr. Co., 60 Md. App. 671, 484 A.2d 302 (1984). Compare Di
Sciullo v. Griggs & Co. Homes, Inc., 2015 WL 6393813, at *6 (E.D.N.C. 2015) (contractor did not
have duciary duty to homeowners with respect to application of deposit toward construction
costs).
7. See Eastover Ridge, LLC v. Metric Constructors, Inc., 138 N.C. App. 360, 533 S.E.2d 827
(2000) (stating that, notwithstanding Article 3 of the contract, the “architect’s constant, close
involvement in the project belies any claim that a ‘relation of trust and condence’ existed
between” owner and contractor); see generally
PhiliP l. Bruner & Patrick J. O’cOnnOr, Jr., cOn
-
structiOn law
§ 6:81 (2002).
pat54645_02_b02_283–496.indd 363 6/28/19 2:01 PM

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT