Hard Hat Case Notes

AuthorBy Christopher M. Burke and Lauren P. McLaughlin
Pages35-37
THE CONSTRUCTION LAWYER 35Fall 2020
Published in The Construction Lawyer, Volume 40, Number 4, Fall 2020. © 2020 American Bar Association. Reproduced with permission. All rights reserved. This information or any portion
thereof may not be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
hard hat Case Notes
By Christopher M. Burke and Lauren P. McLaughlin
Christopher M. Burke is a partner with Varela, Lee, Metz
& Guarino LLP in Tysons Corner, Virginia. Lauren P.
McLaughlin is a partner with Smith, Currie & Hancock
LLP in Tysons Corner, Virginia.
California Court of Appeal Nullies Pay-When-Paid
Provision Temporally Tied to Conclusion of Dispute
Resolution
A signicant amount of case law exists addressing the
application of pay-if-paid and pay-when-paid clauses in
construction contracts. In Crosno Construction, Inc. v. Trav-
elers Casualty. and Surety Company of America, a California
Court of Appeal ruled that a surety could not rely on a pay-
when-paid subcontract clause where that clause permitted
payment to a subcontractor to be delayed until after the
conclusion of dispute resolution between the prime contrac-
tor and owner. 261 Cal. Rptr. 3d 317 (Cal. Ct. App. 2020).
The court reasoned that the potential time period in ques-
tion for payment was unreasonable, effectively forcing the
subcontractor to waive its right to payment.
Crosno Construction was a subcontractor to Clark Bros.,
Inc. in connection with Clark’s construction of two steel res-
ervoir tanks for California’s North Edwards Water District.
Because the project was a public work, Clark was required
to secure a payment bond, and he secured one from Travel-
ers Casualty and Surety Company of America (Travelers).
Crosno began work in March 2014 but was ordered to stop
work in November 2014 due to a dispute between Clark
and the District (which ultimately led to the District’s ter-
mination of Clark’s contract). By that time, Crosno had not
been paid for $562,435 for work performed and for which
invoices had been supplied.
Crosno led a claim under the Travelers payment bond,
but the surety rejected the bond claim as premature. Stat-
ing that the monies owed Crosno were subject to a dispute
between the District and Clark, Travelers relied upon the
following pay-when-paid clause in the subcontract to deny
Crosno’s claim for payment:
If Owner or other responsible party delays in mak-
ing any payment to Contractor from which payment
to Subcontractor is to be made, Contractor and its
sureties shall have reasonable time to make payment
to Subcontractor. “Reasonable time” shall be deter-
mined according to the relevant circumstances, but
in no event shall be less than the time Contractor
and Subcontractor require to pursue to their legal
remedies against Owner or other responsible party
to obtain payment, including (but not limited to)
mechanics’ lien remedies.
Crosno led suit against Travelers in state court and
sought summary judgment on the unenforceability of the
pay-when-paid clause. Crosno argued that the pay-when-
paid provision should be unenforceable because Crosno
never executed a waiver that would have impacted rights
under the payment bond. Crosno cited California Civil Code
§8122, which states:
An owner, direct contractor, or subcontractor may
not, by contract or otherwise, waive, affect, or
impair any other claimant’s rights under this part,
whether with or without notice, and any term of a
contract that purports to do so is void and unen-
forceable unless and until the claimant executes and
delivers a waiver and release under this article.
The trial court awarded summary judgment in favor of
Crosno, and Travelers appealed. Travelers’s argument before
the trial and appeals courts was that Crosno’s rights under
California Civil Code §8122 were not impaired by the sub-
contract’s pay-when-paid clause because Crosno had not
waived its right to payment; rather, Crosno merely agreed
to a timing structure for receipt of payment.
The court of appeals focused its analysis on the reason-
ableness of the timing structure in the pay-when-paid clause.
The court rst noted that, under California law, pay-if-paid
clauses are not enforceable and are void as against pub-
lic policy. However, pay-when-paid clauses are enforceable
because they “merely [x] the usual time for payment to
the subcontractor, with the implied understanding that the
subcontractor in any event has an unconditional right to
payment within a reasonable time.” (Emphasis in original).
The court deemed the linkage between Crosno’s right
to payment and the resolution of Clark’s dispute with the
District to be unreasonable. The court reasoned as follows:
“If Travelers could invoke the subcontract’s pay-when-paid
clause to postpone its payment bond obligation until some
Christopher M. Burke Lauren P. McLaughlin

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT