Complexities of Consequential Damage Foreseeability with Construction Contracts
| Pages | 25-52 |
| Date | 01 January 2026 |
| Published date | 01 January 2026 |
| Author | Jeffrey P. Aiken,Christian Atteberry |
| Subject Matter | Derecho Público y Administrativo |
Published in The Construction Lawyer Volume 45, Number 1, ©2026 by the American Bar Association. Reproduced with
permission. All rights reserved. This information or any portion thereof may not be copied or disseminated in any form or by any
means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
Forum on Construction Law The Construction Lawyer Winter 2026
25
Complexities of Consequential Damage Foreseeability with
Construction Contracts
By Jeffrey P. Aiken and Christian Atteberry
Jeffrey P. Aiken, J.D., is a recently retired adjunct professor of construction law at the University of
Wisconsin Law School and School of Engineering, having practiced for over 40 years in the construction
field.
Christian Atteberry, J.D., is a recent graduate of the University of Wisconsin Law School.
The authors acknowledge and thank Brian O. Shea of Varela, Lee, Metz & Guarino, LLP, in McLean,
Virginia, for his assistance in finalizing this article and his contributions.
This article is intended solely for use by qualified legal counsel and should not be relied upon as an
accurate statement of applicable law in any given jurisdiction except to the extent in conformity with such
counsel’s own legal research and analysis.
Introduction
“The relationships involved in construction contracts have long posed a unique problem in the law of
contracts.”1 This is due, in no small part, to the nature of construction contracts—specifically, the reality
that with most large construction projects, some terms of the contract must change following the initial
entry of the relationship. As this article explains, it is this potential that gums up the works when it comes
to determining foreseeability and, ultimately, the recoverability of consequential damages:
Unlike other contract settings, in construction projects, changes are often ordered after the award of
a contract. “Design may prove to be inadequate. Methods specified become undesirable. Materials
designated become scarce or excessively costly. From the owner’s planning standpoint, program or
budget may change. Natural events may occur that necessitate changes. For any of many reasons it
often becomes necessary to direct changes after the contract has been awarded to the contractor.”2
. . . [E]very project of any significance (and many minor projects as well) will require changes to the
work and, thus, to the price and time of performance as well.3
In general, absent contractual authorization (i.e., a changes clause), an owner is not entitled to change
a contract to address practical difficulties that may arise after it is entered.4 A “changed” contract is a
new contract. Moreover, even with a changes clause,5 the owner will be restricted to changes within the
original scope of the contract.6
But again, the daily reality is that construction projects, and the corresponding contracts, do change,
either expressly (i.e., through a written change order) or constructively through changed work
requirements.7 Moreover, changes to a construction contract often result in claims for damages where
compensation may be justified, with some claims being for direct damages8 and other claims being for
more remote or consequential damages.9
Published in The Construction Lawyer Volume 45, Number 1, ©2026 by the American Bar Association. Reproduced with
permission. All rights reserved. This information or any portion thereof may not be copied or disseminated in any form or by any
means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.
Forum on Construction Law The Construction Lawyer Winter 2026
26
As a general principle, to recover either direct or consequential damages for breach of contract, the
claimed damages must be foreseeable at the time of entering the contract.10 Almost by definition, direct
damages will be foreseeable upon entering the contract; however, the same cannot be said of consequential
damages. While not necessarily different from the general requirement for foreseeability, a rule has been
commonly recognized as though specific to consequential damages: namely, that consequential damages
(a/k/a “consequentials”) must be reasonably foreseeable at the time of entering the contract.11 This
is straightforward enough but not so simple to apply. Is the time of entry into the contract the stated
effective date or the date the last party signs it? Also, for purposes of determining the foreseeability of
consequential damages, what happens if a project achieves partial performance without a signed written
contract?
Although a large number of standard form construction contracts contain an express waiver of
consequential damages,12 such a provision is not universal. Owners typically want to preserve the right
to recover consequential damages by ensuring there is no direct or indirect waiver of these claims in
their contract.13 This is because a failure to complete a project by its target completion date can cause
significant losses in, among other things, rental income and project carrying costs. Contractors, on the
other hand, often strive to have such a provision excluded because the scope of potential damage liability
could result in an uninsurable loss.
This article explores the various components of foreseeability,14 as well as the impact contract changes
may or should have on the ability to recover consequentials—a determination that, at a trial, is generally
assigned to the jury with little guidance as to how such a determination should be made.15 There is little
uniformity in judicial formulations of foreseeability—beyond requiring that foreseeability be measured
at the time of entering the contract.16 However, various jurisdictions ignore many of these issues by
simply characterizing consequential damages as “losses that are the natural and probable results of the
breach”17 or “those additional damages that were contemplated by both parties at the time they made the
contract.”18 At a jury trial, it is then up to the jury to figure out what this means.
In addition to discussing the various components, and sometimes competing interpretations, of
foreseeability, this article argues that the current approach to determining foreseeability is flawed. An
instruction stating that consequential damages are “losses that are the natural and probable results of
a breach” is impossible for a jury to apply with any degree of reliability. Instead, this article argues for
an alternative approach to determining foreseeability, and to address current deficiencies, in the form of
a special verdict sheet with specific questions. Finally, this article concludes with recommendations for
contractor’s counsel, together with a scenario flowchart and accompanying analysis.
The Major Foreseeability Approaches
The Hadley Foreseeability Test versus the “Tacit Agreement” Test
Any analysis of foreseeability, and the issues surrounding foreseeability, must start with the seminal
decision in Hadley v. Baxendale.19 In Hadley, a mill owner failed to inform its insurance carrier of the
significance of a broken crankshaft to the mill’s operation. As a result of this failure to inform, both
parties, in eect, were precluded from pricing in the risk of lost mill profits stemming from a broken
crankshaft. As a result, the court precluded a damages award.20
It should be noted that the Hadley distinction between direct and consequential damages is framed as a
disjunctive: namely, the damage must either arise naturally from the breach or reasonably be within the
contemplation of both parties at the time of making the contract.21 While further guidelines were not
prescribed for how the latter should be determined, the court did lay out the underlying rationale for a
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting