An analysis of causes of delay and cost overrun in construction of hydropower project
| Published date | 01 August 2022 |
| Author | Tamoor Azam,Wang Song Jiang,Sohail Ahmed Malik,Saqib Yaqoob Malik,Memoona Nilofar,Zaheer Abbas,Ihsan Ullah |
| Date | 01 August 2022 |
| DOI | http://doi.org/10.1002/pa.2285 |
ACADEMIC PAPER
An analysis of causes of delay and cost overrun in construction
of hydropower project
Tamoor Azam
1
| Wang Song Jiang
1
| Sohail Ahmed Malik
1
|
Saqib Yaqoob Malik
2
| Memoona Nilofar
3
| Zaheer Abbas
1
| Ihsan Ullah
4
1
Department of Management Sciences and
Engineering, School of Management and
Economics, Kunming University of Sciences
and Technology, Kunming, China
2
College of Economics and Management,
Northeast Forestry University, Harbin, China
3
Department of Business Administration,
Karakoram International University, Gilgit,
Pakistan
4
Department of Sociology, Yunnan University
of Nationalities Kunming, Kunming, China
Correspondence
Tamoor Azam, Department of Management
Sciences and Engineering, School of
Management and Economics, Kunming
University of Sciences and Technology,
Yunnan, China.
Email: tamoorazam@hotmail.com
This research precisely analyzes the delay causes of one of the most delayed hydro-
power project in Pakistan. In this study, grey relation analysis has been employed
which has strong analytical ability, in the process of grey relational analysis calcula-
tion, the same weight cannot fully reflect the optimality of evaluation, so we have
used the entropy weight method to improve it, at the same time, we have used full
information reflected by the evaluation index. The socioeconomic problems which
are delaying this project (Diamar-Basha dam) which include poor resettlement plan
for local people, compensation of land, threat of cultural heritage, and ecological
impacts of this project. It gives quantitative analysis by taking into account several
issues in infrastructural project activities like historical and geographical disputes
between local people and Governments, their socioeconomic impacts on affected
population due to lack of finance and land use conflicts. The deeper roots behind the
excusable delays of construction of the Diamar-Basha dam are discovered in its true
spirit while the putative reasons are decorated how this project get into such a pre-
dicament and further delay in construction of dam will make it a mirage project.
1|INTRODUCTION
Pakistan is facing severe energy crises for last few decades because
the gap between its demand and supply has been increased signifi-
cantly in the past several years and an apt solution of energy bottle-
neck is the key to vigorous, swift, and sustainable development in
energy projects. Moreover, it has generous energy reserves as its
physical hydropower portfolio of Indus Basin consists of 800 sites,
regions across the Gilgit-Baltistan (GB), Azad Jammu and Kashmir
(AJ&K), Khyber Pakhtunkhawa (KPK), Punjab, and Sindh but there is a
skewed distribution in which two regions Khyber Pakhtunkhwa and
Gilgit-Baltistan collectively host 76% (46 GW) of the total 60 GW
potential. The 800 sites are located along more than 125 different riv-
ers and streams which are connected to the Indus Basin Irrigation Sys-
tem (IBIS) (Afreen Siddiqi, Wescoat, & Afridi, 2012) but most part of
the country is still destitute of commercial energy access, so there is a
dire need to develop all form of available resources to reduce
demand–supply gap in the country. There are lot of economic incen-
tives to install hydropower systems but over the last three decades,
an inactive approach has been applied toward construction of hydro-
power projects in Pakistan, hence, share of hydropower in the
national energy mix fell from 60% in 1962–1963 to less than 30% in
2009–2010. This led to increased cost of electricity generation in
Pakistan (Muneer & Asif, 2007). The energy crisis brewed and per-
sisted since 2006–2007 and was at peak during 2011–2012, which is
contemplated to be most terrible power crises that has been faced by
country after inception. Since then, this gap has grown proportion-
ately (Batool & Abbas, 2017). Pakistan's electricity system in last 3–4
decades has been characterized by insufficient generation capacity to
meet demand, high technical and commercial losses that contribute to
“circular debt”and an over-reliance on fossil fuel imports. A major fac-
tor contributing to the widening electricity demand–supply gap has
been the delay in the completion of hydropower projects and com-
plete rely on imported oil while the construction of Diamar-Basha
dam will be one such kind of endeavor to deal energy crisis. Over the
past few decades, construction of hydropower dam encounters delays
in the form of different controversies. They were related to its
impacts on the environment, displacement of communities, time and
Received: 16 June 2020 Revised: 3 July 2020 Accepted: 8 July 2020
DOI: 10.1002/pa.2285
J Public Affairs. 2022;22:e2285. wileyonlinelibrary.com/journal/pa © 2020 John Wiley & Sons Ltd 1of10
https://doi.org/10.1002/pa.2285
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-