$______ VERDICT - BREACH OF CONTRACT - PLAINTIFF CONTRACTOR CLAIMS DEFENDANT ELECTRICAL SUBCONTRACTOR FAILED TO PERFORM WORK CONTRACTED OR PRODUCED DEFECTIVE WORK, FAILED TO SUPPLY LABOR AND MATERIALS AS CONTRACTED, AND CAUSED DELAYS IN PROJECT - DEFENDANT DENIES BREACH; CLAIMS IT COMPLETED WORK PER AGREEMENT AND COUNTERS PLAINTIFF FAILED TO PAY DEFENDANT FOR WORK COMPLETED.

Pages9-10
Attorneys for defendant: Robert J. Cousins and Scott
C. Sankey of Quintairos, Prieto, Wood & Boyer, P.A.
in West Palm Beach, FL.
COMMENTARY
Plaintiff’s counsel stressed the proximity of the decedent’s death
the morning following her treatment by the defendant doctor. The
plaintiff also focused on evidence that the defendant did not refer
the decedent to a hospital or other medical professional. Instead,
the defendant sent her home allegedly failing to recognize an
emergent, urgent and life-threatening medical condition.
However, the defendant’s trial presentation was in direct contrast
to the position put forth by the plaintiff. he defendants offered evi-
dence indicating that there was no indication of the impending
aortic aneurysm and that the defendant physician treated the dece-
dent reasonably and within acceptable standards. The defense also
presented the common-sense argument that the plaintiff could
have and should have taken herself to the emergency room or
called “911” if her symptoms returned or worsened.
At the conclusion of all evidence, in a hard-fought battle, the jury
came out on the side of the defendant and refused to hold the doc-
tor responsible for the decedent’s sudden death.
$266,130 VERDICT – BREACH OF CONTRACT – PLAINTIFF CONTRACTOR CLAIMS
DEFENDANT ELECTRICAL SUBCONTRACTOR FAILED TO PERFORM WORK
CONTRACTED OR PRODUCED DEFECTIVE WORK, FAILED TO SUPPLY LABOR AND
MATERIALS AS CONTRACTED, AND CAUSED DELAYS IN PROJECT – DEFENDANT
DENIES BREACH; CLAIMS IT COMPLETED WORK PER AGREEMENT AND COUNTERS
PLAINTIFF FAILED TO PAY DEFENDANT FOR WORK COMPLETED.
Miami-Dade County, FL
In this breach of contract case, the city’s water
and sewer department hired the plaintiff to
perform work at a project to upgrade its pump
station located at 15701 NW 59th Avenue in
Miami Lakes. In turn, the plaintiff, in turn, hired
the defendant electrical services company to
perform electrical workfortheprojectunder
subcontract. The plaintiff maintained that the
defendant breached its contract with the plaintiff
by failing to provide contracted labor and
materials, performed defective work, failed to pay
mandated payroll wages, and failed to perform its
work in a timely and efficiently manner as
agreed. The defendant denied breaching the
contract and asserted that it had satisfied all the
conditions of the agreement between the parties.
The plaintiff subcontracted the defendant who agreed
to: provide materials and labor sufficient to perform the
scope of the electrical work on the project, including 1)
providematerialandlabortodemoexistingtrans
-
former, meter, control, and SCADA panel, 2) provide
and install new controls, meter, and transformer; 3) pro-
vide material and balor to reconnect/connect SCADA
panel and antenna; 4) provide and install new ATS and
Mini Panel L; and 5) provide material and labor to con-
nect the generator. The plaintiff asserted that the defen-
dant failed to provide or purchase any of the required
materials. As a result, the plaintiff was forced to pur-
chase all of these materials at its own expense with an
understanding that the defendant would be back-
charged for these purchases. In total, the plaintiff pur-
chased materials on the defendant’s behalf for
$67,057. Additionally, the defendant performed defec-
tive installation of electrical piping that required removal
and replacement of a concrete slab to remediate. The
plaintiff performed this work at a cost of $4,710.
The defendant additionally failed to pay certain em-
ployees in accordance with the minimum wage re-
quired by law. The plaintiff was forced to pay the back
wages owed, plus payroll taxes, penalties and costs on
behalf of the defendant. The plaintiff was prohibited
from bidding further jobs while these amounts were
owed, impacting the plaintiff’s overall business. The
plaintiff was forced to pay $6,601 for back wages for the
defendant’s employees, taxes, penalties and costs.
Lastly, the plaintiff maintained that the defendant failed
to perform its portion of the work on time, delaying the
project and causing the plaintiff to incur extended costs.
The defendant asserted that the plaintiff waived certain
conditions or was estopped from asserting said condi-
tions. The defendant counterclaimed that the plaintiff
had agreed to pay the defendant for the work it actually
accomplished as the work progressed and agreed to
make “progress payments” after it received funds from
the client. The defendant maintained that it completed
the work specified in the agreement in November of
2019 and believed the plaintiff had been duly compen-
sated by the client, yet breached the agreement by
failing to remit payment to the defendant when re-
quested. The defendant claimed damages of $42,445
and had been subjected to litigation in the instant case
due to the plaintiff’s breach.
After a bench trial, the court found in favor of the plaintiff
and against the defendant and awarded damages in
the amount of $266,130 to the plaintiff.
REFERENCE
Jones Benitez Corporation vs. Arbor Electrical Service,
Inc. Case no. 2020-010597-CA-01; Judge William
Thomas, 03-04-22.
SUMMARIES WITH TRIAL ANALYSIS 9
Florida Jury Verdict Review & Analysis
Subscribe Now

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT